Fast Speed Transformer Automatic Corrugated Fins Wall Production Line Wear Resistant Long Life Span
Technical Parameters
① plate width: 300mm-1300mm
② corrugation height: 50mm-400mm
③ corrugation pitch: >=45mm
④ plate thickness: 0.5mm-1.75mm
⑤ Forming speed: provided by the bidder
⑥ Power: Offered by the bidder
⑦ control system: electrical, hydraulic and control panels
Composition
1. Transformer corrugated sheet forming machine
Requirements: Both the movable forming plate and the fixed forming plate have two quenching strips for pressing the ends of the corrugated sheet. The position of the bead can be adjusted according to the width of the steel plate.
The process of making ribs in corrugated sheets is shown in two ways:
Main technical parameters of the product
Raw material material SPCC, ST12, ST13, ST14 cold rolled sheet
Wing width 300-1300mm
Wing height 50-390mm
The number of wave fin stiffener slots is up to 2 (according to user needs)
Wing fin pitch 45 ≤ mm
Corrugated sheet thickness 1.0-1.75mm
Wing fin pitch error ± 0.25mm
Molding and welding speed 3~4 waves/min
Wave fin lumen gap 6mm
The total power of the equipment is about 45kW (including two welding machines)
The total weight of the equipment is about 20T
Gas source pressure 0.8Mpa
Air consumption 100L/min
1 The oil to be filled by the product:
(1) kerosene 10 Kg;
(2) Hydraulic oil (L-HM46) 450 Kg;
2 Installation equipment and tools:
(1) There should be a 10 ton crane in the factory (if the vehicle is equipped with an operator);
(2) Impact drill (can install the maximum impact drill φ22);
(3) Impact drills φ10, φ14, φ22;
(4) 200-frame level (accuracy requirement 0.02mm/m);
(5) Crowbar (length 1-1.5m);
(6) cutting machine;
(7) Electric welders and operators;
(8) Air pump (pressure 0.8Mpa, 0.5m3/min).
3 Materials and other items required for installation and commissioning:
(1) Coil 1-2 rolls (for commissioning and final acceptance);
(2) Leveling the horn and flat horn;
(3) Make the equipment foundation according to the basic condition map, and pay attention to the waterproof treatment inside the pit;
(4) Lead the power cord to the incoming terminal of the equipment's electric control cabinet (three-phase five-wire system - -3 phase + neutral line + ground wire, wire cross section ≥ 16mm2).