Malting Packing Production Line With Steeping Tank , Germinating Kilning Box
Germinating And Kilning Box is our long-term production on the basis of malting equipment. It is used of advanced technology and processes, several new products designed to improve with small area, large output, reliable performance, energy saving, durable, easy maintenance, etc. It is widely suitable for malting, beer, grain processing and other major manufacturers of equipment for use.
1. Production capacity: 3T/Batch;
2. Germination air consumption: 600m³/h
3. Kilning air consumption: 4800m³/h
4. Air cool capacity: 5334Kj/h
5. Air heating capacity: 301450Kj/h
6. Germination time: about 120 hours
7. Kilning time: 26-28 hours
1. Overall size: 7000×2300×2600mm
2. Weight: 980kg (excluding motor)
3. Power:1.1kw, speed 1400 rev / min
4. Rotary arm Power:4kw, speed 1400 rev / min
5. screw speed: 8R/min
1. The barley with water pumped malting machine, which will drain the water
2. Spray, malting barley in one machine quickly germinate, germination process to keep the spray, so that the grain required to achieve the degree of steeping, germination while intermittently open air blower timely pass, while carbon dioxide emissions generated germination and germination is completed in about 5 days.
3. Germination is complete, open the fuel hot air blower, direct drying 28-36 hours out of the box in the box.
Machine installation:
Machine requires a solid and smooth cement placed on a flat ground.
Machine lubrication
Where a rotating or moving friction parts should be regularly inject a small amount of oil.
Machine checking
When the new machine factory, the gap has been adjusted to the correct position and size, except in special circumstances generally do not need the user to adjust, but should check for damage and missing parts, and then the following inspection and reinspection.
1, Machine Checking before turning
(1) Tightness and security guards before starting the check belt is reliable, various parts of the fasteners loose.
(2) Check the oil in these parts.
2, Dynamic load transfer checks
(1) View cantilever starter motor rotation direction is correct, whether the required speed.
(2) Carefully observe whether the channeling axis, percussion and other abnormal conditions.
.
(3) No-load operation for at least 15 minutes to check.
(4)Machine Operation
(1) Off gate handle, flow indicators adjusted to the appropriate location.
(2) Starter motor.
(3) Pump the soaked barley to the malt box .
(4) After the end of each day, you should remove the slag machine memory, the machine body and the surrounding clean.
(5) Precautions
(1) Remember first boot backward feed.
(2) Prevent nails, of metal, hard rock mixed with feed.