3 5 7 Ply Corrugated Paperboard Production Line Corrugation Plant
3 5 7 Ply Corrugated Paperboard Production Line Corrugation Plant for making 3 5 7 ply corrugated cardboard
Technology parameters
1 | width | 2000mm | 2 | Design produce speed | 150m/min | |||
3 | Three layer economic speed | ------------------- | 4 | Five layer economic speed | 100m/min | |||
5 | seven layer economic speed | ------------------- | 6 | Maximum order change speed | 80m/min | |||
7 | Longitudinal separation accuracy | ±1mm | 8 | Cross-cutting precision | ±1mm | |||
note | Speed the above targets required to achieve:effective width2000mm,Comply with the following standards and ensure the paper's equipment condition 175 ℃ heating surface temperature. | |||||||
Top paper index | 100g/㎡--180g/㎡ Ring crush index(N.m/g)≥8 (Water containing8-10%) | |||||||
Core paper index | 80g/㎡--160g/㎡ Ring crush index(N.m/g)≥5.5 (Water containing8-10%) | |||||||
In paper index | 90g/㎡--160g/㎡ Ring crush index(N.m/g)≥6 (Water containing8-10%) | |||||||
9 | Flute combination | |||||||
10 | Steam requirement | The maximum pressure 16kg/cm2 | Common pressure10-12kg/cm2 | use4000kg/Hr | ||||
11 | Electricity demand | AC380V 50Hz 3PH | Total power≈350KW | Running Power≈150KW | ||||
12 | Compressed air | The maximum pressure 9kg/cm2 | Common pressure4-8kg/cm2 | use1m3/min | ||||
13 | Space | ≈Lmin80m*Wmin12m*Hmin5m(The actual drawing to provider to provide audited prevail) |
3 5 7 Ply Corrugated Paperboard Production Line Corrugation Plant Customer owned section:
1, Steam heating system:proposal with 4000Kg / Hr of a steam boiler. Pressure:1.25Mpa steam pipeline. 2, Air compressed machine,air pipeline,glue conveying pipe. 3, Power supply,wires connected to the operation panel and line pipe. 4, Water sources,water pipelines,buckets and so on. 5, Water, electricity, gas flush mounting civil foundation. 6, Test with the base paper,corn starch (potato),Industrial use caustic soda,borax and other material. 7, Oil equipment,lubricating oil,hydraulic oil,lubricating grease. 8, installation,commissioning of food, accommodation. And provide installers with the installation. |