Customized Dry Type Shotcrete Equipment Easy Operation User Friendly
Shotcrete Equipment
Prepare for startup Shotcrete Equipment:
Operate the machine for a short time in order to grasp the rotation situation (pay attention to whether the direction of operation is the same as the direction of arrow, pay attention to avoid the heating of friction plate). Check the pressure applied to the sealing plate. First, it is used to lock the nut on the clamping device rod until it is pressed. Then, it is used to tighten 2-3 rings with a wrench until the sealing plate does not leak air.
Parameters of Shotcrete Equipment:
Technical | Parameters | ||||
Model | PZ-5 | PZ-6 | PZ-6F | PZ-7 | PZ-9/WSP |
Throughput(m3/h) | 5-5.5 | 6 | 6-7 | 7 | 9 |
Transport Distance (Tidal Spray) (m) | 200 | 200 | 200 | 200 | 200 |
Applicable Material (Cement/Sandstone) Ratio | 1:3~5 | 1:3~5 | 1:3~5 | 1:3~5 | 1:3~5 |
Applicable Material (Water/Ash) Ratio | ≤0.4~0.45 | ≤0.4~0.45 | ≤0.4~0.45 | ≤0.4~0.45 | ≤0.4~0.45 |
Aggregate size (mm) | φ20 | φ20 | φ20 | φ20 | φ20 |
Working Pressure (MPa) | 0.2~0.4 | 0.2~0.4 | 0.6~0.8 | 0.6~0.8 | 0.6~0.8 |
Feeding height (m) | 1.1 | 1.1 | 1.1 | 1.1 | 1.1 |
Rotor speed (r/min) | 11 | 11 | 11 | 11 | 11 |
Motor Power (KW) | 5.5 | 5.5 | 7.5 | 7.5 | 7.5 |
Motor speed (r/min) | 960 | 960 | 960 | 960 | 960 |
Operation Method of Shotcrete Equipment:
After the preparation work is finished, the mixing material can be added to the machine. The machine operator should first open the main valve, the valve of the upper air duct opens 1/3 circles, and then adjust the air pressure of the lower air duct (to the cyclone) to about 0.05-0.1 MPa (depending on the delivery distance). Then the sprayer opens the nozzle valve and gives the wet rock surface. At this time, the operator can start the machine and start shotcreting. Now the working pressure is about 0.2-0.4 MPa. According to the water-cement ratio of mixtures and the length of conveying distance, after adjusting and determining the wind pressure to the cyclone, the upper air pipe valve is opened again until there is no more material leakage at the machine outlet.