Internal Pipe Coating Equipment,powder painting equipment,Complete in specifications
INTRODUCTION
3PE coating line is to make anti-corrosion of kinds of steel pipes, such as single layer FBE, double layer FBE, double layer PE, double layer PP and 3PE.
The line includes systems of steel pipe transportation, surface disposal, dust catching, pipe heating, electrostatic spraying, coating, water cooling, edge cutting, hydraulic and pneumatic device, detecting and electric controlling system.

Description:
3PE anti-corrosion coating production line means the steel pipe is protected by three layer to prolong the life of use from 5-10years to 50-100years.
First layer is Fusion bonded epoxy layer (FBE> 100µm), the second layer of adhesive (AD) 170 ~ 250µm, the third layer of polyethylene (PE) 2.5 ~ 3.7mm. Present we can made the machinery for diameter range Φ159 ~ Φ1220.
3PE steel pipe outer coating has a high mechanical strength, excellent electrical insulation performance. The merits include high degree of mechanization, process parameters stable, not pollute the environment, etc. In recent years, the intensive of the pipeline corrosion engineering has been widely used.
3pe have Long-term corrosion resistance
FBE components have excellent adhesion to steel, providing excellent long-term corrosion resistance and protection for pipelines operating at moderate temperatures.
If desired, low application temperature (LAT) FBE can be selected as a primer to ensure low preheating conditions and long-term integrity of high strength steels (X80 or higher)
In addition, 3LPE systems have excellent cathodic stripping resistance, reducing the life cycle cost of cathodic protection

No. | Name | Set |
A. Derusting Equipment |
1 | Pipe-converying Equipment | 1 |
2 | Shot Blast Cleaning Machine | 1 |
3 | Cyclone Dust Collector | 1 |
4 | Pulse dust collector | 1 |
5 | Centrifugal exhaust fan | 1 |
6 | Rust removal equipment PLC | 1 |
B. Coating equipment |
1 | Coating transfer equipment | 1 |
2 | IF heating device | 1 |
3 | Powder spraying device | 1 |
4 | Automatic loading dryer | 2 |
5 | SJ-65/30 Extruder | 1 |
6 | SJ-180/30 Extruder | 1 |
7 | Hot melt adhesive extruder die | 1 |
8 | PE sheet extruder head mold | 1 |
9 | Hot melt adhesive/PE sheet coating device | 1 |
10 | Environmental Protection Ventilation equipment | 1 |
11 | Cooling Spray equipment | 1 |
C.Platform Equipment |
1 | Steel pipe platform | 1 |
2 | Post-rust removal transition platform | 1 |
3 | Product tube storage platform | 1 |
4 | Hydraulic Equipment | 3 |
D.Groove Equipment |
1 | PE Beveling Machine | 2 |
2 | Hydraulic Lifting and Turning Machinery | 1 |
3 | Hydraulic Equipment | 1 |
4 | PLC | 1 |
E.Compressed air Equipment |
1 | Screw Air Compressor | 1 |
2 | Cold dry machine | 1 |
3 | Precision filters | 3 |
4 | Gas tanks | 1 |

The technological processes employed by Huashida Machinery for the 3LPE coating of steel pipes involve a series of meticulous steps designed to ensure the highest level of quality and durability. Here's a detailed overview of the process:
- Upload Pipes:
- The process begins with the loading of the steel pipes onto the production line. This step ensures that the pipes are positioned correctly and ready for processing.
- Pipes Screw Conveyor:
- Once loaded, the pipes are transported through the production line using a screw conveyor. This efficient system gently moves the pipes forward, allowing for continuous and uninterrupted processing.
- Rust Removal via Intermediate Frequency Heating:
- To ensure a smooth and even coating, it's crucial to remove any rust or impurities from the pipe surface. This is achieved through intermediate frequency heating, which raises the temperature of the pipe surface to effectively burn off rust and contaminants.
- Epoxy Powder Coating:
- Following rust removal, the pipes are coated with an epoxy powder primer. This layer acts as a corrosion-resistant barrier, providing a strong foundation for the subsequent coatings.
- Outer Layer Solidification & Polyethylene Coating:
- Next, the pipes undergo the application of the outer layer, which consists of a solidified coating and a polyethylene layer. The solidification process ensures that the coating adheres firmly to the pipe surface, while the polyethylene layer provides additional protection against corrosion and wear.
- Cooling Spray:
- After the coating is applied, the pipes are sprayed with a cooling solution to rapidly cool and harden the coating. This step is crucial for achieving a durable and long-lasting finish.
- Pipes Screw Conveyor (Continued):
- The cooled pipes are then transported further along the production line using the screw conveyor, ready for the next stage of processing.
- Grinding Pipes:
- To ensure a smooth and even surface finish, the coated pipes undergo a grinding process. This step removes any imperfections or excess coating material, leaving a flawless surface.
- Send & Unload Pipes:
- Finally, the processed pipes are sent to the end of the production line and unloaded, ready for use in various applications.
Throughout this process, Huashida Machinery employs state-of-the-art equipment and rigorous quality control measures to ensure that every pipe is coated to the highest standards. Our team of experts oversees every step of the process, ensuring that our customers receive only the best products and services.