Specifications
Brand Name :
Ze Xu
Model Number :
based on customer's needs
Certification :
ISO9000
Place of Origin :
Yanshan, Hebei, China
MOQ :
1Pcs
Price :
USD 10 per piece
Payment Terms :
T/T
Supply Ability :
100,0000 tons per month
Delivery Time :
3-7 Working day
Packaging Details :
Wooden box, pallet or according to customer requirements
Material :
aluminum, copper, iron
Thickness :
5mm、6mm、8mm、10mm
Length :
According to customer needs, according to pipe diameter
Width :
Not less than 8% of the pipe diameter
Description

Sputtering Aluminum Target Plate For Steam Purge Test In Power Plant

After the pipeline system is installed, air or steam can be used to blow it according to the working conditions of its working medium and the degree of contamination of the inner surface of the pipeline. The general requirements for pipe purging are:

Equipment and pipelines that do not allow purging should be isolated from the purging system.

Before the pipeline is purged, the orifice plate, flange-connected regulating valve, main valve, throttle valve, safety valve, instrument, etc. should not be installed. For the above-mentioned valves and instruments connected by welding, the bypass should be adopted or the seal should be removed. protection measures, etc.

The order of purging should be carried out in the order of main pipe, branch pipe, and dredging pipe.

The dirt discharged by purging shall not pollute the environment, and it is strictly forbidden to discharge it at will.

A forbidden area should be set before purging.

No other operations that affect the cleaning shall be performed after the pipeline has been purged qualified.

Aluminum target plate for purging experiment, the specifications and models are customized according to customer needs, Zexu company makes aluminum target plate:

1. After the strength test of the pipeline system, before the air pressure tightness test, purging and cleaning should be carried out in sections
2. The purging method should be determined according to the use requirements of the pipeline, the working medium and the degree of dirt on the inner surface of the pipeline. Liquid or gas pipelines with a nominal diameter greater than or equal to 600mm should be cleaned manually, and liquid pipelines with a nominal diameter less than 600mm should be cleaned manually. Use water to clean the gas pipeline with a nominal diameter of less than 600mm, it should be purged with air. Steam piping should be purged with steam, and non-thermal piping should not be purged with steam. The purging of the gas is generally carried out in sequence by the main pipe, the branch pipe, and the dredging pipe.
3. Before the pipeline is flushed, a detailed flushing plan should be prepared and carried out according to the system section.
4. Equipment and pipelines that are not allowed to be purged are separated from the purge system.
5. After the pipeline cleaning is qualified, in addition to the specified inspection and recovery work, no other work that affects the cleaning of the pipe shall be performed, and the "Pipeline System Blowing Record" shall be filled out.

Sputtering Aluminum Steam Blowing Target Plate For Steam Purge Test In Power Plant

Sputtering Aluminum Steam Blowing Target Plate For Steam Purge Test In Power Plant

Sputtering Aluminum Steam Blowing Target Plate For Steam Purge Test In Power Plant

Send your message to this supplier
Send Now

Sputtering Aluminum Steam Blowing Target Plate For Steam Purge Test In Power Plant

Ask Latest Price
Brand Name :
Ze Xu
Model Number :
based on customer's needs
Certification :
ISO9000
Place of Origin :
Yanshan, Hebei, China
MOQ :
1Pcs
Price :
USD 10 per piece
Contact Supplier
Sputtering Aluminum Steam Blowing Target Plate For Steam Purge Test In Power Plant
Sputtering Aluminum Steam Blowing Target Plate For Steam Purge Test In Power Plant
Sputtering Aluminum Steam Blowing Target Plate For Steam Purge Test In Power Plant

Hebei Zexu Pipe Manufacturing Co., Ltd.

Active Member
5 Years
hebei, cangzhou
Since 2016
Business Type :
Manufacturer, Exporter, Seller
Total Annual :
10000000-50000000
Employee Number :
>100
Certification Level :
Active Member
Contact Supplier
Submit Requirement